A lot of work needs to be done both in OSBL and ISBL. The WWT unit is facing some upset due to the waste being sent from recent shutdown. This means that preparations need to be made to prepare for the worse. Nutrients need to double dosed...
In ISBL, we faced difficulty in starting up due to the Reactor feed line plugging. This means a lot of work.
Thanks to our friends from Shift B for helping out...
Below are pics taken on our first night...



On our second night shift, the plant is already running smooth.
Mohan took the night off along with Mafa. So, Thaufik took over as Relief.
We welcome back Saufi to the shift. As we all know, he went to perform Umrah. He brought 'kopiah' for each one of us.
All in all, it's a good two night shifts for us all...


~AmiN~
No comments:
Post a Comment